Auditor General
of British Columbia
OFFICE OF THE
Vancouver Island
Highway Project:
Planning and Design
Ministry of Transportation
and Highways
1996/1997
:Report 3
Performance Audit
LOCATION:
8 Bastion Square
Victoria, British Columbia
V8V 1X4
OFFICE HOURS:
Monday to Friday
8:30 a.m. – 4:30 p.m.
TELEPHONE: (250) 387–6803
Toll free through Enquiry BC at: 1–800–663–7867
In Vancouver dial 660–2421
FAX: (250) 387–1230
INTERNET:
bcauditor@oag.aud.gov.bc.ca
INTERNET HOMEPAGE:
Further information and reports at:
http://www.aud.gov.bc.ca/
Auditor General
of British Columbia
OFFICE OF THE
Canadian Cataloguing in Publication Data
British Columbia. Office of the Auditor General.
Vancouver Island Highway Project : Planning and design
(Report ; 1996/97: 3)
“Performance audit.”
ISBN 0-7726-3073-9
1. Vancouver Island Highway Project - Evaluation. 2. British Columbia. Ministry
of Transportation and Highways - Evaluation. 3. Highways planning - British
Columbia - Evaluation. 4. Roads - Economic aspects - British Columbia.
II. Title. II. Series: British Columbia. Office of the Auditor General. Report;
1996/97: 3.
TE27.B7B74 1996 388.1’1’097112 C96-960360-6
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Auditor General of British Columbia
Auditor General’s Comments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
Highlights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
Audit Purpose and Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
Overall Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
Key Findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
Detailed Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
Assessment of Designs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .23
Highway Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .27
Design Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .33
Standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .39
Ministry Response . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .47
Appendices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .49
A 1996/97 Audit Reports Issued to Date . . . . . . . . . . . . . . . . . . . . . . . . .51
B Office of the Auditor General: Audit Objectives and Methodology
for Performance Auditing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .52
table of contents
1
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Auditor General of British Columbia
This report is my third report to the
Legislative Assembly for the 1996/97 year. It
provides the results of my Office’s performance
audit of the Vancouver Island Highway Project,
a $1.3 billion upgrade to the Island Highway
corridor between Swartz Bay (north of Victoria)
and Campbell River. Our audit looked at the
facility planning and design phases of the
project, as decisions made during these phases—
particularly during facility planning—determine
the bulk of the capital costs of the highway, and
significantly affect its lifecycle costs.
Since 1987, there have been a number of
reports dealing with large highway projects in
British Columbia. One of them, released in that
same year, the Report of the Commissioner Inquiry
into the Coquihalla and Related Highway Projects by
Douglas L. MacKay, was highly critical of the
way the Ministry of Transportation and Highways planned,
managed, and reported on major highway construction
projects. Commissioner MacKay found that there was no
comprehensive long-range highway capital plan, the selection
of projects was not based on objective criteria, and highway
planning was not integrated with overall transportation
planning.
Following that report, the ministry undertook to
improve the way it managed capital projects by employing
the “proven project management practices” recommended
by MacKay. It also initiated a province-wide inventory and
evaluation of all modes of transportation, and announced
the “Freedom to Move” transportation planning process.
In 1990, my Office conducted an audit of the ministry’s
process for managing major capital projects, focusing on the
steps that the ministry had taken to implement the project
management principles and practices to which it had
committed itself. We found that the ministry had significantly
improved the way it managed capital projects, but that it
needed to make additional improvements before it would
be able to ensure that it was getting good value for money
on capital projects.
In 1991, we conducted an audit of highway planning.
Our report noted that the ministry had introduced new
planning and budgeting processes, but that the new
processes did not yet meet a reasonable standard for
ensuring that good value is achieved from highway capital
auditor general’s comments
expenditures. The processes were, however, significantly
better than previous ones and efforts were being made to
make further improvements.
In this audit, which we conducted in early 1996, we
assessed what the ministry has done to ensure that its
planning and design processes for the Vancouver Island
Highway provide good value for the money spent. The
decisions taken at this stage of the capital project drive the
lifecycle cost of the highway that is ultimately built.
I wish to thank the Ministry of Transportation and
Highways staff, and other government personnel, for the
cooperation and assistance provided to my audit staff
during the course of their work on this audit.
George L. Morfitt, FCA
Auditor General
Victoria, British Columbia
November 1996
2
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
3
highlights
5
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Auditor General of British Columbia
An audit of the planning and design of the Vancouver Island Highway Project
For any highway capital project, planning and design
decisions determine what will be built, where it will be
built, when it will be built—decisions that effectively
determine most of the cost of, and cash flow required for,
building the highway.
The Vancouver Island Highway Project is a $1.3 billion
upgrade to the Vancouver Island Highway corridor, including
both upgrading existing highway and new construction,
between Swartz Bay (north of Victoria) and Campbell River.
To ensure that the highway eventually constructed will
provide good value for money, it is important that the
planning and design processes in place for this project
are appropriate and are followed.
Audit Purpose and Scope
The purpose of this audit was to assess whether the
Ministry of Transportation and Highways has taken
appropriate steps to ensure that the designs for the
Vancouver Island Highway provide good value for money.
“Appropriate steps” include:
planning and design management processes which
provide reasonable assurance that needs are identified
and designs developed to address those needs in a cost-
effective manner; and
a suitable framework of technical standards within which
the planning and design processes occur.
We looked mainly at the period since November 1988,
when the Minister of Transportation and Highways
announced that the government would upgrade the
highway, and that the project would be completed by 1996.
This announcement signaled the beginning of the project as
it exists today.
Our audit focused on the planning and design of
specific sections of the project. We did not review the
broader issues of transportation planning, or the decision
of the government to make upgrading the Vancouver Island
Highway its number one highway capital priority in 1988.
Our examination was performed in accordance with
value-for-money auditing standards recommended by the
Vancouver Island Highway
Project: planning and design
6
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Canadian Institute of Chartered Accountants, and accordingly
included such tests and other procedures as we considered
necessary in the circumstances.
Overall Conclusions
We concluded that the designs for the Vancouver Island
Highway will provide good value for money within the
context of current ministry standards and guidelines.
Although there was insufficient planning during early
phases of the project, the Vancouver Island Highway Project
team has addressed most of the deficiencies during the
subsequent planning and design phases. The team has
also developed appropriate design management processes,
including an adequate Quality Management program.
The ministry’s planning and design standards, including
guidelines for establishing functional classification of
highways, are generally adequate. However, we believe the
ministry would benefit from reviewing these standards and
their application to ensure that they promote cost-effective
planning and design decisions.
Key Findings
The ministry established an appropriate organizational structure
and project management processes to deliver the Vancouver Island
Highway Project
The ministry set up a separate project team, within
the Major Projects Branch, to deliver the Vancouver Island
Highway Project. It also established a joint venture with
UMA Engineering Ltd., a private sector firm, for the
management of the project. Ministry employees work with
UMA employees in an integrated fashion. This arrangement
has provided the ministry with access to private sector
project management tools, while at the same time developing
the project management skills of ministry employees.
The ministry also created a Project Management
Committee and a Technical Review Committee to facilitate
communications between the Vancouver Island Highway
Project and the rest of the ministry. The Project Management
Committee was established to deal with policy and project
scope, schedule, and budget issues. The Technical Review
Committee was established to deal with proposed variances
from design standards and other technical issues.
In 1991, the ministry commissioned a firm of project
management consultants to conduct a management audit
of the Vancouver Island Highway Project. The consultants
concluded that, in general terms, the project was being well
managed, although they made a number of suggestions for
7
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Auditor General of British Columbia
improvements. In 1994, the same consultants were asked to
assess progress and to review some additional areas not
covered in the original audit. Again they confirmed that the
Vancouver Island Highway Project was functioning well.
They made a number of recommendations, including
implementation of a Value Engineering program. The
ministry acted on many of these recommendations, including
the implementation of a Value Engineering program.
The designs for the Vancouver Island Highway Project will provide
adequate value for money
The audit included a review of the results of the
planning and design processes for a number of project
segments. The project segments selected included both
bridges (stream crossings and grade separations) and
highway segments that were at different stages of completion,
and in different parts of the project. To help us in assessing
the appropriateness of the designs and to evaluate whether
they would provide value for money, we contracted the
services of technical experts in highway design.
We found that the designs we reviewed provide
adequate value for money within the context of current
ministry standards and guidelines. The designs were
developed in accordance with the established design criteria,
and satisfied the project objectives. Technically and
functionally, they are consistent with the established criteria
that govern highway or bridge design and, when necessary,
any significant departures from those criteria were adequately
investigated, explained, and documented.
For all the project segments we reviewed, alternatives
were developed and evaluated during the planning and
design process. On one of the project segments, two of the
design criteria—functional classification and design speed—
were amended following preliminary design studies, when
it was recognized that the project segment, as originally
planned, would result in significant overcapacity.
However, an adequate capital management program
requires that design alternatives be compared using
estimated lifecycle costs as well as expected performance
of each alternative. We found that only limited attention
was given to lifecycle costs during development of designs.
Earlier Value Engineering reviews conducted on the project designs
might have resulted in better value for money
Value Engineering is a formal, organized procedure
for reviewing a project in order to identify alternatives that
can provide a more cost-effective product without reducing
performance or reliability.
8
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Value Engineering studies were carried out as part of
a pilot project in 1995. The studies indicated that the designs
of the sample of the project segments included in the pilot
project provide adequate value for money. The project team
implemented a number of recommendations made as a
result of the studies, and has incorporated other suggestions
into the project’s planning and design processes.
Although the studies also identified other potential
savings opportunities, these were not explored because the
studies were, for the most part, conducted at a late stage of
design and the costs of redesign were prohibitive, public
commitments had been made, or fiscal year spending targets
made delay unattractive. Conducting Value Engineering
studies earlier in the planning and design process would
have permitted consideration of a broader range of
recommendations. The pilot project committee recognized
this fact and indicated that Value Engineering studies
should be conducted during preliminary design, before
public information sessions are conducted, and then again
later in the process but before commitments are made to
major design features.
System planning was incomplete when the project was announced
System planning is planning for the highway network
of the province as a whole or of a region (such as Vancouver
Island). Its purpose is to ensure that the province’s system
of highways is developed in a logical and coherent manner,
balancing transportation needs throughout the province
with resources available for development. The need for
good planning was emphasized in the 1987 Report of the
Commissioner Inquiry into the Coquihalla and Related
Highway Projects.
In the 10 years before the announcement of the
Vancouver Island Highway Project in 1988, a number of
studies called for improvements to the Vancouver Island
Highway, based on safety and traffic volume concerns.
These studies were not sufficiently detailed—from an
engineering point of view—to permit accurate estimates of
the costs of alternative improvement options. The 1988
project announcement, however, created a public expectation
that the project would have certain features (such as a
freeway to north of Campbell River), even though sufficient
planning had not yet been done to determine what those
features might cost or whether they were necessary or
appropriate.
The scope and budget for the Vancouver Island Highway
Project has changed considerably over the life of the project.
As the project has progressed, better information about
needs, costs, and financial limitations has transformed the
preliminary cost estimate for the project from “in excess of
9
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Auditor General of British Columbia
$600 million” to approximately $1.3 billion and has also
significantly affected what will actually be constructed.
A combination of public input, financial pressures, and
emerging needs has resulted in a reshaping of the scope
of the project; adding to the project in some areas, reducing
the scope of work in other areas.
The Vancouver Island Highway Project is a program
of work along a corridor. The schedule for the project was
determined more by when sections of the project were able
to be built rather than by which sections were the most
needed. Initially, insufficient consideration was given to
staging the project so that highway capacity would become
available as demand grew. However, capping of the overall
project budget and recent reviews required to meet debt
management targets have resulted in scope reductions and
the staging of some parts of the project.
Facility planning for the project is satisfactory
Facility planning is planning that determines exactly
what will be built—for example, two lanes or four lanes, an
intersection or an interchange, and so on. Despite deficiencies
in the early planning for the Vancouver Island Highway
Project, facility planning for the project has been adequate.
The planning procedures are clearly described in the terms
of reference in contracts with planning consultants, and
project management documentation describing policy and
procedures for facility planning is currently available.
Relatively little facility planning remains to be done,
with most of the major planning studies having been
completed by 1991. Project segments planned since then
include the Millstream Connector, the South Courtenay
Connector, and the South Campbell River Connector.
Public communication has been a significant element
in the planning of the project. Community liaison groups
have been established, open houses held, and information
published in newspaper advertisements and flyers. The
project team has sought to identify and balance the interests
of various groups.
Design management for the project is appropriate and adequate
Design is the detailed definition of what will be built
and how the construction process will be organized. The
Vancouver Island Highway Project’s design management
procedures are adequate. Procedures have been well
documented and are set out in the draft Implementation
Plan. The project’s design management process is similar
to that used in other jurisdictions and for other ministry
projects. Project-specific procedures are set out in the terms
of reference of each design contract.
10
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
The project also has an adequate quality management
program. Consultants are required to ensure adequate
quality control procedures are built into their design
processes, and Vancouver Island Highway Project design
coordinators monitor consultants to ensure that quality
control procedures are effective. Design deliverables are
reviewed by a multi-disciplinary team of Vancouver Island
Highway Project staff, and certain technical issues may be
referred for review by other ministry staff. Designs produced
by consultants are expected to meet the ministry’s current
design standards.
The ministry’s design standards are generally adequate
Ministry design standards are comprehensive, well
documented, and within the range of those used in other
North American jurisdictions. However, there are
opportunities for improvement. Lifecycle cost analysis is
not always considered in the development of standards. As
well, the current standards have been developed primarily
for rural, rather than urban, highways and do not recognize
regional variations.
In 1995, the ministry hired a consultant to review its
design standards. The consultant reported that ministry
standards were consistent with those in other jurisdictions
and that a general reduction in standards was not warranted.
However, the consultant identified some specific areas for
review. Subsequently, the ministry began a process to review
its standards with a focus on the potential for cost savings.
The results of that review have been positive, with a
number of opportunities for cost savings found.
The Vancouver Island Highway Project team has
questioned the application of ministry design standards in
specific cases, and presented proposals for variance to the
Technical Review Committee. The project team believes
that the standards are being applied too rigidly. Other
ministry staff respond that, if a viable alternative is suggested,
a variance from standards will be approved. Only limited
use is made of formal risk and cost-benefit analyses to
determine whether a request for variance should be approved.
Decisions about functional classification, design speed,
and level of service of a highway determine a large part
of the costs of a project. The functional classification of
highways, a planning decision, is guided by a manual
which indicates the type of highway that should be built to
serve specific traffic volumes at an acceptable level of service.
This guideline reflects the ministry’s policy with respect to
the level of service that will be provided to highway users,
subject to resource limitations.
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
13
Auditor General of British Columbia
The Vancouver Island
Highway Project
The Vancouver Island
Highway Project (Exhibit 1)
involves upgrading the existing
highway between Swartz Bay
(north of Victoria) and Parksville,
and building a new highway from
Parksville to Campbell River. In
addition to the new 125 km
highway from Campbell River to
Parksville, the project includes a
new 21 km parkway along the
western edge of Nanaimo, the
upgrading of 87 km of the Trans
Canada Highway between
Nanaimo and Goldstream Park to a
four-lane divided arterial highway,
and the upgrading of most of the
highway between Goldstream Park
and Victoria to a four-lane freeway.
A number of improvements have
also been made to the highway
between Victoria and Swartz Bay.
History of the Project:
1981–1987
In 1981, the Ministry of
Transportation and Highways
began a review of the long-term
transportation requirements of
Vancouver Island. As part of the
review, a ministry consultant
prepared a report entitled Study of
the Projected Growth of the Economy of
Vancouver Island, 1981–2001. The
consultant’s report presented an
overview of the Vancouver Island
economy, examined the role of
Vancouver Island in the context
of the economy of the province,
reflected upon industrial
development and regional growth,
and prepared population forecasts
for Vancouver Island.
At about the same time, the
ministry initiated a “Traffic Analysis
and Forecasts” project. The objective
of this project was to assemble an
inventory of Vancouver Island’s
existing transportation services
and traffic volumes, and provide
baseline traffic projections to the
year 2001. The report, published in
September 1983, projected traffic
levels for the year 2000 to increase
30–80% over 1980 levels.
In the fall of 1986, the
government announced its
commitment to a major highway
improvement program on
Vancouver Island. The following
spring, the ministry produced a
report entitled A Development
Strategy for the Vancouver Island
Highway, in which it proposed a
10–year, $511 million program of
new highway construction and
improvements to the existing
highway. The program was to
include construction of a four–lane
inland highway from Parksville to
Campbell River, a four–lane
freeway bypass around Nanaimo,
and four lanes on the existing
Island Highway between Nanaimo
and Victoria, including the stretch
of highway through Goldstream
Park. The report indicated that cost
estimates were preliminary only.
The Project Since 1988
The current project can be
traced back to announcements
made by the government in
November 1988. At that time, the
background
14
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Exhibit 1
Vancouver Island Highway: Project Overview
Source: Ministry of Transportation and Highways
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
15
Auditor General of British Columbia
Glossary of Terms
Project scope: The scope of a highway project describes the physical characteristics of the highway or structure that will
be built, including the physical boundaries and a list of the significant elements included in the project.
Functional classification: Functional classification describes the type of highway (freeway, expressway, arterial or
secondary) theoretically required to provide an adequate level of service for a particular daily volume of traffic.
Level of service: A measure of the smoothness of traffic flow ranging from level “A”( free flow generally associated with
low density traffic) to level “F” (very high density, stop-and-go conditions, long delays).
Design year: The year established as a planning horizon.
Freeway: A divided highway with two or more lanes in each direction. Access to a freeway is via interchanges only.
Expressway: A divided highway with two or more lanes in each direction. Access to an expressway is via intersections at
public roads.
Arterial highway: A major highway of two or more lanes, not always divided, along which access roads to adjacent
private properties may be restricted.
Parkway: An urban expressway.
Intersection: A meeting or crossing of two roads at the same elevation. Through traffic, or movement from one road to
another, requires traffic on one of the roads to yield to traffic on the other, and is often controlled by traffic lights.
Interchange: A meeting or crossing of two roads, whose grades are separated (that is, there are different elevations at the
crossing point). Movement from one road to the other is accomplished by ramps and merging streams of traffic, without
traffic on either road being required to stop.
Global planning: Multi-modal transportation planning for the whole province or an area within the province (Vancouver
Island, for example)
System planning: Planning for the highway network within the province or a smaller area.
Facility planning: Planning for a specific road, section of road, interchange, intersection, bridge, tunnel, etc.
Planning study: A study to identify and prioritize requirements for new or upgraded highways. Planning studies consider
safety concerns, user needs, economic development issues, population or demographic changes, urban planning, and
other transportation modes.
Planning criteria: Planning criteria summarize existing conditions and future conditions considered to be desirable,
affordable, and achievable. In their early stages, planning criteria are a guide for planners; when completed, they are a
summary of the planning done, and a guide for designers. Planning criteria define the “problem” that a project is
expected to address.
Corridor study: An evaluation to select a preferred corridor from a number of alternatives. A corridor identifies, in
general terms, where a highway might be built. Corridor studies compare alternatives on the basis of identified needs,
natural obstacles, environmental and social issues, and cost-benefit analyses.
Route study: A route study is the next level of refinement after a corridor study. A route study evaluates alternative road
alignments through a corridor, refining the issues considered in the corridor study.
Preliminary design: Preliminary design identifies possible alignments, develops evaluation criteria, selects one alignment,
and develops a design for that alignment.
Functional design: After site surveys and geotechnical investigation, functional design refines the preliminary
alignment design.
Design criteria: One of the products of the preliminary design process, the design criteria establish parameters within
which designers must work. Design criteria identify the number and configuration of lanes, design speed limits, access
requirements and limitations, and social and environmental constraints.
Detailed design: The development of sufficiently detailed information to define construction requirements.
Design standards: Design standards are a collection technical requirements that describe (sometimes in general terms,
sometimes in specific terms) the parameters within which a design must be developed.
Staging: Completing construction of a facility over a period of time rather than all at once, for the purpose of matching
supply and demand and deferring costs.
project had an eight-year schedule,
with completion to be by 1996 and a
preliminary cost estimate “in excess
of $600 million” (1988 dollars). In
January 1989, that preliminary
estimate was used in a presentation
to Treasury Board. The project
was approved in principle, with a
requirement that detailed plans and
funding needs be provided.
Since 1988, the scope of the
project has been revised many
times. Some items—such as the
Millstream Connector—have been
added; others— such as some work
on the Patricia Bay Highway
between Victoria and Swartz Bay
and on the Millstream Road to
Goldstream Park section of the
Island Highway—have been
deferred. Goldstream Park was
explicitly excluded from the project
in the 1988 announcement because
of environmental sensitivities in the
area. Changes to scope have been
made for many different reasons,
including: local traffic needs,
projected traffic volumes, increased
property acquisition costs, and debt
management limitations.
Details about the evolution of
the scope, schedule, and budget
for the project are contained in
Exhibit 5 (which can be found
at page 44 of this report).
Project Funding and
Expenditure to Date
The project is being funded
through the BC Transportation
Financing Authority, a Crown
corporation established April 1,
1993, by the Build BC Act. Before
1993, the Ministry of Transportation
and Highways was responsible for
funding the construction and
maintenance of all provincial
highways. Since 1993, it is the
Transportation Financing Authority
that funds highway capital projects
and approves project scope,
schedule, and budget changes. The
Transportation Financing Authority
has a formal agreement with the
ministry to have the ministry
manage the planning, design, and
construction of the Vancouver
Island Highway Project (Exhibit 2).
At the time of our audit, the
Transportation Financing Authority
was responsible for project scope,
schedule, and budget changes
involving up to $10 million.
16
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Rush hour (pre-construction) Victoria approaches
Courtesy: Ministry of Transportation and Highways
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Changes in excess of $10 million
must go to Treasury Board for
approval.
At the end of June 1996,
the budget for the Vancouver
Island Highway Project was
$1,296.3 million (1996 dollars), an
increase of $32.7 million over the
previous quarter, reflecting the
addition of the Duke Point
interchange to the project and
adjustments to show the budget in
1996 dollars. To the end of June 1996,
17
Auditor General of British Columbia
Exhibit 2
Vancouver Island Highway Project Relationships
Source: Ministry of Transportation and Highways
BC Transportation Financing
Authority (Crown Corporation)
Highway
Constructors
Ltd.
Vancouver
Island Highway
Project
(MoTH)
General
Contractors
Sub–
Contractors
serves as owner and
financier
subsidiary of BCTFA
employer of workforce
provides labour
relations framework
negotiates collective
agreement
enters into contractors
and sub-contractors to
provide labour
manages project
undertakes
planning
property acquisitions
design
construction
tenders work packages
and awards contracts on
behalf of BCTFA
construct sections
of highway
secure contracts through
public tendering process
purchase labour
from Highway
Constructors Ltd.
complete portions of
work packages for
general contractors
purchase labour
from Highway
Constructors Ltd.
$671.4 million had been spent on
the project (Exhibit 3).
At the start of the 1996/97
fiscal year, spending limits were
established at $175.6 million and
$159.5 million for fiscal years
1996/97 and 1997/98, with the
expectation that the project would
be completed in fiscal year 2000/01.
In June 1996, the government
announced a freeze on capital
spending pending a review of its
capital programs (including the
Vancouver Island Highway). The
review is expected to be completed
by the end of December 1996.
Project Management
In December 1987, in the
Report of the Commissioner Inquiry
into the Coquihalla and Related
Highway Projects, Commissioner
Douglas L. MacKay reported the
results of his inquiry into the issues
relating to the estimated and actual
costs of highways constructed in
recent years in British Columbia. He
was critical of the way the Ministry
of Transportation and Highways
planned, managed, and reported on
highway construction projects. Many
of his criticisms were directed, in
particular, at the way the ministry
managed large construction projects.
He recommended that the ministry
adopt “proven project management
practices for major projects.”
In the wake of Commissioner
MacKay’s report, the ministry
undertook to change the way it
managed highway construction
projects. It effected an extensive
ministry reorganization, made a
commitment to the principles of
project management as practiced
in the private sector, and created
the Planning and Major Projects
Department, with responsibility
for transportation planning and
the management of selected major
projects, particularly those expected
to cost more than $50 million.
These projects are referred to as
“major” projects.
In 1988, the Vancouver Island
Highway Project was consolidated
under the Major Projects group of
the Ministry of Transportation
and Highways. Although the
Vancouver Island Highway Project
office is part of the ministry, it is a
separate operating unit providing
almost all the services required for
the delivery of a major project
(Exhibit 4).
18
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Exhibit 3
Financial Information at June 30, 1996 ($ Millions)
Source: Ministry of Transportation and Highways, Vancouver Island Highway Project, First Quarter Report, Fiscal 96/97
Actual
Budget Forecast Expenditure
Engineering/Administration $ 151.1 $ 172.9 $ 126.3
Land Acquisition 281.4 318.8 216.3
Construction 782.9 758.7 328.8
Contingency 80.9
$1,296.3 $1,250.4 $ 671.4
ADM Planning
& Major
Projects
Deputy
Minister
ADM
Operations
Executive
Oversight
Committee
Technical Review
Committee
(TRC)
Chief
Highway
Engineer
ADM
Administration
Director
Region 6
Region 6
Oversight
Committee
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Partnership with
Private Sector
In the late 1980s, when the
Vancouver Island Highway Project
was in its early stages, the Ministry
of Transportation and Highways
did not possess state-of-the-art
project control systems for
managing the scope, quality, cost,
and schedule of a project the size of
the Vancouver Island Highway
Project. As well, in addition to the
other changes in the ministry, the
government had recently
introduced an Early Retirement
Incentive Program that resulted in
the loss of a large number of the
ministry’s most senior and
experienced people.
19
Auditor General of British Columbia
Exhibit 4
Vancouver Island Highway Project/Ministry Administration Structure
Source: Ministry of Transportation and Highways
Project
Principal
Assistant
Project
Director
Communications
Manager
Project
Director
Project Managers
Capital Region
Goldstream to Nanaimo
Nanaimo to Parkway
Parksville to Mud Bay
Mud Bay to Courtenay
Courtenay to Campbell River
Resource Managers
Environmental Management
Design Management
Project Services
Property Acquisition
Construction Management
To ensure that the project had
adequate resources—both human
and systems—the ministry
requested proposals from the
private sector to provide project
management services. UMA
Engineering Ltd. was selected,
and the ministry entered into an
agreement with the firm in June
of 1990.
The project is currently being
managed by a project team within
the Ministry of Transportation and
Highways that is a hybrid of
ministry employees and employees
of UMA Engineering. The project
team is headed by the Project
Director, who is an employee of the
Ministry of Transportation and
Highways, and each of the sub-
projects has been assigned to a
Project Manager, who is an employee
of either the ministry or UMA
Engineering. The sub-projects are:
Capital Region
Goldstream to Nanaimo
Nanaimo Parkway
Parksville to Mud Bay
Mud Bay to Courtenay
Courtenay to Campbell River
Project managers are
responsible for delivering their
projects within a set scope, schedule,
and budget, and in accordance with
ministry standards.
Transfer of Knowledge
and Technology to
the Ministry
The creation of a hybrid project
management team to manage the
Vancouver Island Highway Project
was partially predicated on a
recognition of the need for the
ministry to acquire the management
systems and expertise required
to adopt the “proven project
management practices” referred to
by Commissioner MacKay. UMA
Engineering brings its project
management expertise and systems
to the project, and knowledge is
being transferred to ministry
employees as they work with UMA
employees.
One of the deliverables of the
Vancouver Island Highway Project
is an organized body of knowledge
about how to manage a major
project. This is to be contained in
the Vancouver Island Highway
Project Implementation Plan. The
plan manual will describe the
policies and procedures for
managing the planning, design,
and construction components of
a project within the standards
established by the ministry and
within the scope, schedule, and
budget parameters established by
the government. It will also set out
how a project should be organized,
implemented, monitored, and
controlled, with guidance on project
scope, budget, and scheduling
management, and on the
development and reporting of
project information for monitoring
and project management decision-
making purposes.
The Implementation Plan was
in draft form at the time of our
audit, and due to be published
before the end of 1996. It is
expected to evolve and be updated
over the life of the project.
Project Management
Audits
In 1991, the ministry retained
a consulting firm to perform a
management audit of the
Vancouver Island Highway Project.
The audit was intended to:
20
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
“Review and assess
the appropriateness and
effectiveness of the functions,
policies, practices and controls
(financial, administrative and
technical) currently in place
for the management of the
Vancouver Island Highway
Project.”
The consultants concluded, in
their March 1992 report, that the
Vancouver Island Highway Project
had a sound project management
organization in place, with project
management systems functioning
properly to provide appropriate
information for management
decision-making. They approved
of the use of a hybrid team of
professionals to provide project
management and to enable the
ministry to maintain direct control
of the project while tapping the
resources of state-of-the-art project
management personnel and
technology. The consultants also
concluded that the scope, schedule,
and budget goals established for the
Vancouver Island Highway Project
were being managed within
reasonable tolerances and with
adequate accountability. However,
they found there was no framework
within the ministry for quality
management.
The consultants made a
number of recommendations they
believed would enhance the overall
effectiveness of the project
management team and the
project management process.
Recommendations included:
implementation of a Quality
Management strategy to provide
the proper balance between those
responsible for executing projects
within scope, schedule, and budget
and those responsible for the quality
of results; clarification of the division
of responsibilities between the
Vancouver Island Highway Project
project team and the professional
services branches of the ministry;
and a quality assurance focus
within the project team to ensure
that the work of retained design
consultants met required standards.
The quality management
recommendations of the consultant
were consistent with comments
made by the Auditor General in
1990. We noted that one result of the
decision to do more business by
contract was that the ministry’s
quality assurance processes would
have to become more formal and be
supported by staff with enough
experience to carry them out. Part
of the reason for contracting with
UMA Engineering to provide
project management services to the
Vancouver Island Highway Project
was to ensure the adequacy of
the ministry’s quality assurance
processes.
In 1994, the ministry asked the
consulting firm to perform a follow-
up review of the Vancouver Island
Highway Project. The consultants’
report (issued in December 1994)
concluded that, since the earlier
audit, the project had made
significant progress in organizational
evolution. Overall improvements
had been achieved in all functional
areas, and project performance had
been good.
Also noted was that the
traditional ministry approach to
project delivery—separating the
design phase from the construction
phase, with limited engineering
involvement in the construction
phase—had changed significantly
on the project so that construction
21
Auditor General of British Columbia
managers had become responsible
for approving design documents
before they were issued for tender.
The consultants recommended that
this progress be supported through
the implementation of a program to
have design consultants involved
throughout construction and,
specifically, to have designers review
all design changes made during
construction to ensure that the
integrity of the design is maintained
and that design criteria are met.
The review identified a number
of potential risk areas, including
again the lack of a ministry-wide
quality management program, and
suggested the implementation of a
Value Engineering program for the
project. Value Engineering was
implemented in regard to the
project in mid-1995. Although it
was undertaken too late to provide
maximum benefits for those project
segments reviewed as part of a pilot
project, the results of the process
were worthwhile. The project team
has subsequently conducted Value
Engineering reviews at an earlier
stage on other project segments.
During the course of our
review, we found that project
management structures and
processes have continued to evolve
over the life of the project to
address the issues raised in the
MacKay Commission report and in
the various consultants’ reports.
Organization of
This Report
We have organized our
findings into four sections:
Assessment of Designs
Highway Planning
Design Management
Standards
22
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Adequate planning and design
management processes can provide
reasonable assurance that adequate
results (designs) will be produced.
However, a review of the actual
results of the planning and design
process provides a better assessment.
As part of our audit
examination, we reviewed the
results of the planning and design
process for a number of project
segments on the Vancouver Island
Highway Project.
The project segments selected
included both bridges (stream
crossings and grade separations)
and highway segments that were at
different stages of completion, and
in different parts of the project. To
help us in assessing the
appropriateness of the designs and
to evaluate whether they would
provide value for money, we
contracted the services of technical
experts in highway design.
We expected to find designs
that should meet functional
requirements at projected levels
of service and forecasted traffic
volumes; designs that are within
scope and budget parameters; and
designs that incorporate lifecycle
cost minimization objectives. We
looked for cost-benefit analyses
(including lifecycle cost analyses) of
alternatives.
Conclusion
We concluded that the designs
reviewed offer adequate value for
money within the context of current
ministry standards and guidelines.
Technically and functionally, they
are consistent with the established
criteria that govern highway or
bridge design and, when necessary,
any significant departures from
such criteria have been adequately
investigated, explained, and
documented.
However, if the Value
Engineering reviews had been done
earlier in the planning and design
process, it might have been possible
to achieve better value for money
from the projects.
Findings
Meeting Requirements
We found that the designs for
the project segments included in
our sample, whether preliminary
or detailed, were developed in
accordance with the established
design criteria and satisfied the
project objectives.
For several of the project
segments reviewed, design criteria
variances were considered and
assessed before confirming the
appropriateness of the proposed
design criteria. On one of the
project segments, two of the design
criteria—functional classification
and design speed—were amended
following preliminary design studies,
when it was recognized that the
project segment, as originally
planned, would result in significant
overcapacity.
Documentation of changes
to design criteria or functional
requirements is one area that needs
improvement. In several of the
project segments, changes were
made to design criteria (functional
classification and design speed)
23
Auditor General of British Columbia
assessment of designs
during the design process, but the
reason, or sometimes the approval,
for the change was not
documented.
Considering Alternatives
We found that for all the
project segments we reviewed,
alternatives were developed and
evaluated during the planning and
design process. For example:
configuration and staging
variations were considered for
the Craig’s Crossing Interchange;
alignment alternatives were
considered for the Transfer Beach
to Jones Road section of the
highway through Ladysmith;
different structural solutions
were considered to deal with
severe geotechnical conditions
found at the Colwood Overpass;
several alignment alternatives for
the Campbell River crossing were
developed and assessed; and
level crossings and other
alternatives were reviewed in an
effort to avoid construction of
bridges for logging roads
crossing the Inland Island
Highway corridor.
Cost-Effective Designs
Cost-effective designs provide
good value for money. The term
“cost-effective” describes an
appropriate balance between
functionality of an item and the
lifecycle cost of the item.
Functionality of a highway or a
bridge is measured according to
how well it performs its intended
function of providing for safe and
swift movement of vehicles over the
lifetime of the asset. Lifecycle cost
of a highway or bridge includes the
total of capital and maintenance
(including periodic rehabilitation)
costs over its lifetime.
The cost-effectiveness of design
alternatives can be assessed by
comparing the functionality and
estimated lifecycle cost of each
alternative. This has not been done
for all of the Vancouver Island
Highway Project designs, nor is it
part of the ministry’s current design
process requirements. We believe
that such analyses should be
included as a required element in
the ministry’s design process.
We found no evidence of
imbalance between the functionality
of designs and their capital cost.
However, we noted that only
limited attention had been given to
lifecycle costs during development
of the designs.
Least Lifecycle Costing
In 1991, we suggested that the
ministry must do better costing if
good value-for-money decisions
were to be made. We noted that, for
highways, the quality of the initial
construction and the rate of wear
are directly related. The stronger
the initial construction, the longer
the road will last, and the less
maintenance and rehabilitation it
will require. However, high quality
costs more money initially. The best
value for money is achieved when
quality that minimizes the lifetime
cost of the road is chosen.
Our report acknowledged that
the determination of least lifetime
cost was a difficult task, but we
noted that the ministry was starting
to give more consideration to the
concept in its decision-making.
24
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
In this audit we found that
explicit consideration of lifecycle
costing was still not part of the
design process for any of the project
segments reviewed.
Recommendation
The ministry should include, in
addition to estimated capital cost,
the estimated lifecycle cost of each
alternative being evaluated during
the design process.
Value Engineering on
the Vancouver Island
Highway Project
In response to the project
management consultant’s
recommendation that the Vancouver
Island Highway Project perform
Value Engineering, a pilot project of
nine Value Engineering reviews—
which were considered to cover a
representative sample of project
segments—was conducted by
several Value Engineering
consultants in the summer of 1995.
25
Auditor General of British Columbia
Value Engineering
Value Engineering is a formal, organized procedure for reviewing a project in order to identify alternatives that
can provide a more cost-effective product. The purpose of such a review is to ensure identification of the most
cost-effective designs without reducing performance or reliability. In use for approximately 50 years in the
United States, it evolved out of the need to find substitutes for materials that had become scarce during the
Second World War.
Value Engineering evaluates a proposed design against the functional requirements the project is intended to
meet. Cost-effective alternatives are identified and evaluated. However, emphasis is not simply on reducing the
cost of a project—rather, it is to identify savings without reducing performance or reliability. The goal is to
identify design solutions that provide the greatest value over the long term, not designs that simply result in
reduced capital cost but may increase overall lifecycle costs.
This type of analysis is inherent in all good design practice. The added value of a separate Value Engineering
review comes from having a team of experts take an independent look at a design. Because of the cost in
assembling a team of experts for even a short review, however, the project must be of sufficient magnitude and
complexity to warrant the cost of a review.
The literature advocating Value Engineering promises savings ranging any where from 5 to 50% of construction
and operating costs. The greatest returns have been reported from reviews that took place early in the project—
during planning or preliminary design. If a review takes place early in a project, impact on project schedule is
minimized, costs of changing plan documentation is less than if changes are made later, and there is less
chance that “pride of ownership” of ideas will interfere with consideration of alternatives.
The success of any Value Engineering review is dependent on the extent of the implementation of the review
team’s recommendations. Implementation can be limited by a number of factors. If, for example, maintaining
an announced schedule for project completion is more important than achieving best value for money,
recommendations that conflict with such priorities will not be implemented. Other limiting factors are an
inherent resistance to change and concern about risks associated with innovation.
Even a Value Engineering review that does not identify opportunities for achieving more cost-effective designs
can be useful, providing an owner, or other stakeholder, with the benefit of independent confirmation that the
original design is likely to provide good value for money.
Six highway segments and
three bridge project segments were
selected from the project, providing
a sample that represented the
range of geographic distribution
and project type. The total
estimated construction cost of
these project segments was
$125 million (approximately 15% of
the total project construction cost at
that time).
As a result of the nine reviews,
a number of recommendations were
implemented, resulting in estimated
benefits of more than $2 million.
Other recommendations valued at
over $1 million were deferred for
further review and possible
implementation. The cost of the
Value Engineering reviews was
$630,000.
Review of Value
Engineering Studies
We reviewed the results from
seven of the Value Engineering
studies that were part of the 1995
pilot project. We looked in
particular at the extent to which
some recommendations had been
implemented and the reasons for
not implementing others.
We found that, in general,
Value Engineering recommendations
had been implemented where
possible. For those that were not
adopted, the reason included one or
more of the following:
the recommendation included
changes to design criteria;
the recommendation did not
comply with ministry policies or
standards;
further detailed review by the
project team revealed that the
estimated savings identified by
the Value Engineering studies
were not available either because
of implementation costs or
because the potential savings had
been overstated;
other ministry branches were the
final decision-makers, and
implementation of the
recommendation would have to
be reviewed from a province-
wide perspective; or
previous commitments had been
made to the public and to local
municipalities.
We concluded that the Value
Engineering studies, in several
cases, had been undertaken too late
in the design process. Nevertheless,
the results of the studies have been
worthwhile to the Vancouver Island
Highway Project from both an
economic and a process
improvement point of view.
Since the pilot project in 1995,
the project team and other areas of
the ministry have conducted several
Value Engineering studies with
positive results. Value Engineering
guidelines are now in place as part
of the planning and design process
for future portions of the Vancouver
Island Highway Project. We believe
that similar guidelines should be
applied to other ministry projects.
26
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
The decision to build or
upgrade a highway is based on an
analysis of the transportation needs
and goals of the provincial and local
governments. The initial decision
about whether or not to proceed
with a particular project should take
into consideration: identified need
for the highway, preliminary public
input, and known constraints
(economic, environmental, etc.).
Once the decision to proceed has
been made, a few basic planning
decisions—decisions about the
classification and design speed of
the highway, the level of service that
will be provided, and the extent to
which construction of the project
will be staged—effectively determine
much of the cost of a project.
We expected to find: an
assessment of needs and how those
needs will be addressed by the
Vancouver Island Highway
Project; planning based on reliable
information and reasonable
forecasts; and a reasonable process
for receiving and incorporating
public input. We also expected an
appropriate evaluation of costs and
benefits—monetary and non-
monetary—of alternatives.
Conclusion
When the project was
announced, neither a global
transportation plan nor a highway
system plan existed for the
province, or even for Vancouver
Island. Many of the early planning
decisions for the Vancouver Island
Highway Project that would have
been part of system planning were
thus made without adequate
information. Furthermore,
documentation of early planning
decisions is incomplete—many
decisions appear to have been based
on professional judgment without
formal analysis. Despite these
deficiencies in needs identification
and evaluation of cost and benefits
of alternatives, once the project was
approved by the government the
detailed system and facility
planning for the Vancouver Island
Highway Project has been adequate.
Findings
The Decision to Undertake
the Vancouver Island
Highway Project
Our audit did not include a
review of the decision to undertake
the Vancouver Island Highway
Project. The decision to proceed
with the project—to allocate much
of the ministry’s capital funding to
the project—was an issue of
resource allocation and a decision
made by government.
Early Planning
In early November 1988, the
Minister of Transportation and
Highways announced that the
government would be spending
more than $200 million on the first
phase of the Vancouver Island
Highway Project. The announcement
said that the Vancouver Island
Highway Project would include a
major upgrade from Swartz Bay to
Nanaimo and a new Inland Island
Freeway from Nanaimo to Campbell
River. The project was to be
completed by 1996 at a total cost in
excess of $600 million. Details of
the construction schedule were
also provided.
27
Auditor General of British Columbia
highway planning
The information on which the
announcement was based was
limited, originating from conceptual,
rather than detailed, planning
studies. One of the drawbacks of
making announcements with
limited information is that the
announcement creates expectations
that further review may determine
are not practical or possible. This
was the reason that Commissioner
MacKay recommended, in late 1987,
that “in the event a major capital
highway project must be announced
at a conceptual level of development,
the government [should] ensure
that expenditure authorizations be
limited to interim amounts sufficient
to develop project planning to a
level such that proper estimation
of cost and definition of scope can
be made.”
At the time of the
announcement, Treasury Board had
not approved either the scope or
the budget for the project. Not
until October 1989 did the ministry
prepare a Treasury Board submission
seeking approval for a scope of
work similar to that announced.
With the more detailed information
then available, the proposed project
budget was $1.4 billion.
In late November 1988, the
Premier announced the formation
of regional transportation planning
task forces to prepare regional
transportation plans. The report of
the Vancouver Island Transportation
Task Force, released in June 1989,
concluded that, for safety and
regional economic development
reasons, the Vancouver Island
Highway Project was the main
priority for the region.
Justification for the Project
The decision to upgrade the
Vancouver Island Highway was
based on apparent deficiencies—
specifically, safety and mobility—
of the existing facility. Functional
classification and design speed for
the proposed highway were
initially set at a high level to
improve safety and mobility factors.
Anticipated population growth for
Vancouver Island was also a factor.
However, traffic volumes were not
the determining factor for initial
decisions about what would be
built. The Minister’s 1988
announcement anticipated the
functional classification for the
highway without consideration of
projected traffic volumes.
No detailed analysis of costs
and benefits was conducted until
1991, when a ministry-commissioned
consultants’ report indicated that,
based on the project scope and
budget at the time, the project had a
positive net benefit. The consultants
found that the project was largely
justified on the basis of lives saved
and injuries and property damage
avoided as a result of improvements
to the highway. This, the consultant
concluded, combined with the
benefits of reduced travel time,
increased user comfort and
convenience, fuel savings and
reduced vehicular emissions, made
the Vancouver Island Highway
project “a cost-effective expenditure
of funds.”
In 1993, another consultant’s
review also concluded that there
would be positive net benefits from
the project, although the consultant
found that time savings made up
60-70% of user benefits. This
consultant made the findings using
the ministry’s recently-developed
procedures for measuring the direct
economic benefits and costs to
society of selected portions of the
Vancouver Island Highway Project.
28
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Facility Planning
The purpose of facility
planning is to assess alternatives
and, ultimately, to identify the
optimum configuration and route
for a highway.
We found that each of the
subprojects has undergone in-depth
study and the information used for
planning has been comprehensive.
However, forecasting methods have
varied between subprojects, and
planning assumptions have not
been well documented in some
cases. Although the different
methods have yielded reasonable
results, we believe that a more
uniform approach, using
standardized evaluation criteria,
should be used to ensure consistency
between project segments and to
facilitate comparisons between the
Vancouver Island Highway Project
and other projects.
Early planning studies
thoroughly reviewed the options,
taking into account not only
engineering, topographical, and
geotechnical considerations, but
also environmental, socio-economic,
and cultural (e.g., ancient burial
grounds) factors. However, some
options seem to have been eliminated
based on professional judgment and
experience, without formal analysis.
For example, upgrading Highway
19 from Parksville to Courtenay was
considered to be impractical because
of the high cost of land along the
highway. That option was therefore
excluded from early planning
studies. Little use was made of
formal economic review techniques
such as cost-benefit analysis, and in
some cases the criteria used to
choose between alternatives were
not clear.
29
Auditor General of British Columbia
McKenzie Interchange (Victoria)
Courtesy: Ministry of Transportation and Highways
Although traffic forecasting
was done, little emphasis was
placed on the forecasts for shaping
the proposed project . Building
the Inland Island Highway from
Parksville to Courtenay in stages,
as traffic volumes increased, was
discussed, but rejected without
formal analysis by the project team.
The Courtenay to Campbell River
section of the Inland Island
Highway was reduced from a
freeway to a two-lane expressway
with protection for future
expansion to a four-lane freeway;
but, for the most part, the early
plans changed little from the
scope as announced. Staging
considerations concerned the order
of construction rather than the need
to bring capacity on stream as
demand required.
Another problem we
encountered was in following the
decision-making trail in some
projects. In one case, we noted a
major change in direction between
sequential planning studies, but no
documentation of how or why the
decision was made.
Summary of Planning
Up to 1991
In June 1991, a consulting firm
was commissioned to “provide a
written record within one document
of the planning work done to date
on the [Vancouver Island Highway
Project], a description and economic
analysis of the project as proposed
at this time, [and] a conceptual plan
for the long range development of
the corridor.”
The review, which predated the
involvement on the project of most
of the Vancouver Island Highway
Project project team, was
commissioned because of the
apparent lack of detailed
planning—or at least an apparent
lack of documentation of such
planning—before many of the
basic decisions were made. The
consultants reviewed and
documented: available traffic
assumptions and conditions for a
20 to 25 year horizon; levels of
service with planned and committed
highway improvements; planning
criteria used for various project
segments; alternatives considered
and criteria used to evaluate them;
transit alternatives; and
environmental issues.
The report, entitled
Comprehensive Planning Assessment:
Vancouver Island Highway Project,
was issued in June 1991. It noted
that no plan had been developed
for improvements through
Goldstream Park, despite the
apparent need to deal with the
bottleneck created by a two-lane
road through the park joining
proposed four-lane facilities on
either side of the park. Also
described were the limitations
imposed by the decision to upgrade
the existing corridor between
Goldstream and Nanaimo, and the
need to identify a corridor for a
new highway on a new alignment
at some point in the future (with
specific concerns raised about the
level of service available to traffic
passing through Duncan).
Nevertheless, it concluded that
“despite the obvious lack of an
overall planning process which
would clearly have been desirable,
the major decisions and directions
chosen in pursuit of the project are
well founded.”
30
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Planning Since 1991
There has been only limited
planning undertaken for the
Vancouver Island Highway Project
since 1991.
The Victoria Approaches
section of the project was halted in
May 1991 to permit the Capital
Regional District to conduct its own
transportation planning exercise. It
did this by developing a multi-
modal plan, a highway systems
plan, and then specific facility plans.
One of the outcomes of the process
was that the Millstream Connector
was added to the project in 1993.
The Planning Framework
Since 1991, the ministry has
made significant improvements to
the planning process in several
areas. It has developed a number of
guidelines for planning, including a
functional classification study and a
guidebook on the appraisal of
highways investments. It has also
developed a model for conducting
cost-benefit analysis—the User
Benefit Cost Spreadsheets model—
and is enhancing its techniques for
multiple accounts evaluation, a
method of evaluating economic
and social costs. These tools will
bring a greater degree of uniformity
to the methodologies used in
planning studies.
Until recently, consultants
maintained a proprietary interest
in any model they developed for
traffic forecasting. The ministry,
therefore, could not re-use an
existing model unless it belonged to
the consultants currently doing the
work. To address this, the ministry
has been developing a formal
framework for planning, and now
has guidelines for planning and
formats for modeling. Models now
become the property of the ministry
so that successive consultants do
not have to recreate the models for
each planning study. However,
many of the ministry’s policy and
procedure documents for planning
have yet to be finalized.
The ministry is also in the
process of developing a provincial
highway plan based on measurable
performance factors and criteria,
with data about how well those
criteria are being met or are likely
to be met in the future. The ministry
hopes to use the plan to identify
current and projected deficiencies in
the highway system, and actions
required to address the deficiencies.
A draft of the strategy component
of the plan was produced in the
summer of 1995, but had not yet
been finalized at the time of
our audit.
The Vancouver Island Highway
Project team has documented its
planning procedures for inclusion in
a project management manual and
these procedures have been used on
recent planning projects on the
Vancouver Island Highway Project.
The procedures are consistent with
industry standards.
Since 1993, budget pressures
have had an impact on the project.
Certain planning decisions have
been revisited, staging of
construction has become a primary
consideration, and other
opportunities to reduce or defer
costs have been identified. For
example, initial construction of the
Admirals-McKenzie interchange
on the Trans Canada Highway
north of Victoria will retain some
characteristics of an signalized
intersection, rather than becoming
a full interchange. This will save
about $15 million in capital costs.
31
Auditor General of British Columbia
In summary, it is clear that
significant progress has been made
in planning since the project was
announced, particularly in the area
of global and systems planning.
Facility planning has been adequate
—if not always consistent—although
there are gaps in the documentation
of the planning process.
Public Consultation
Communication with the
public has been a major feature of
this project. On past projects, the
ministry has been criticized for
holding public information sessions
in which the ministry seemed to be
simply informing the public of
what was going to be done, without
providing any opportunity for
feedback or discussion. During
early public meetings to introduce
the Vancouver Island Highway
Project, ministry staff met with
unanticipated public resistance to
the project as proposed. People
envisaged a “Los Angeles-type
freeway system” and the immediate
reaction was negative. The ministry
response was to hold such meetings
earlier in the planning process and
to change the meeting format so
that the public could comment on
the project alternatives. Initially, the
Public Affairs Branch of the ministry
conducted public information
sessions, but when the Vancouver
Island Highway Project office was
established, a Communications
Manager position was created with
responsibility for planning and
implementing an effective public
information campaign for the project.
The project team has moved to
an “open house” format—perceived
to be a more positive forum than
public meetings—which gives the
public an opportunity to talk with
staff and express their concerns in a
relatively quiet, more personalized
atmosphere. The project team
developed printed materials and
circulated questionnaires to gauge
public reaction to proposals. As
project staff became more aware of
the public’s desire to provide input,
questions became more open-
ended and opportunities for input
came at an earlier stage in the
planning process.
To ensure that a wide range
of community interests were
represented, liaison committees
were also set up in each community,
consisting of representatives of the
municipal council, the head of
Engineering for the municipality,
up to four representatives of
community-based groups within
the municipality, and the highway
project’s Project Manager for that
section of the project.
The process for receiving
public input appears to be
reasonable, and the Vancouver
Island Highway Project team has
responded to many suggestions
from the public, local politicians,
and MLAs.
The ministry also set up
Vancouver Island Highway Project
information offices in Colwood,
Nanaimo, Courtenay, and Campbell
River. These are open to the public
year round. As well, newspaper
advertisements and information
supplements are distributed
periodically, advising the public of
progress and upcoming events.
32
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Highway planning evolves
into highway design. After corridor
and route selection decisions have
been made, a project moves into
an iterative design process.
Preliminary design defines the basic
characteristics of the route selected.
Functional design follows
preliminary design, providing more
detail in terms of alignments,
intersections, and right-of-way
requirements. The final design
details the construction specifications
necessary to permit contractors to
bid on the construction of the various
projects that make up a highway.
We expected to find a good
design management process,
structured and managed in a
manner to ensure that designs are
consistent with approved project
scope and will result in highways
and bridges that are both
functionally effective and cost-
effective. A good design
management process is one in
which there is: a clear process,
clearly defined responsibilities, and
an adequate quality assurance
program, including an adequate
design review mechanism.
Conclusion
The project team has an
adequate process to manage
design. However, we believe that
improvements could be made over
the long term if the ministry had
a formal program to assess the
functional effectiveness and cost-
effectiveness of designs as built, and
to capture the experience in its
corporate memory.
Findings
The Design
Management Process
Design policy and procedures
for the project have been
documented and published in one
form or another since 1992. The
process, as set out in the draft
Implementation Plan, includes all
possible steps that could be
required in the design of a section of
highway or a structure (such as a
bridge or interchange). The
process—intended to be used as a
guideline—is adapted to suit the
specifics of each contract, and the
process to be followed is clearly laid
out in the terms of reference for
each design assignment.
In 1994, the consultant engaged
to review the Vancouver Island
Highway Project’s project
management practices concluded
that the design management
procedures, as drafted, were
“comprehensive and provide an
adequate basis for the management
of the Vancouver Island Highway
Project design process and, when
followed, ensure a consistent design
approach by Vancouver Island
Highway Project design consultants.”
Our review has confirmed this
assessment, and found that the
required procedures are being
followed.
Consultants are required to
produce a series of deliverables
which are subject to review by
Vancouver Island Highway Project
staff at several points during the
design process. The project staff
involved in the review vary
33
Auditor General of British Columbia
design management
according to the facility being
designed.
The process used on the
Vancouver Island Highway Project
is much like that used on the
ministry’s other projects, and in
other jurisdictions, although some
extra reviews are performed.
Design consultants confirmed that
they are comfortable with the
project’s design management
process and have a clear
understanding from their contract
documents about what is required
of them.
Responsibilities for Design
A number of distinct groups
have specific responsibilities related
to the project: the Vancouver Island
Highway Project staff, the ministry
Professional Services staff, the
ministry regional staff, and the
consultants.
The Vancouver Island Highway
Project staff are responsible for
ensuring that the design is consistent
with the approved scope and budget,
and that the design complies with
ministry technical standards.
The ministry Professional
Services staff provide technical
advice and policy direction to the
project, and review any proposed
variances from ministry standards.
At one time, Professional Services
staff were more involved with
design review, but as the project
team has developed their
involvement has declined. The
recent restructuring of the ministry
has made it clear that, in future,
Professional Services staff will
have a monitoring role and
provide technical advice only
when requested.
Ministry regional staff provide
input to the project based on their
local knowledge and experience.
In some cases, they also provide
specific technical and professional
design services to the project.
Consultants do most of the
actual design work, in accordance
with the terms of reference
contained in their contracts. They
are responsible for producing a
design that meets ministry design
standards, and for providing
sufficient justification to support
any proposed variances from those
standards.
Two committees have been
established to provide liaison
between the Vancouver Island
Highway Project management team
and the rest of the ministry.
The Project Management
Committee was set up in 1990 to
enable ministry oversight of the
project, provide guidance and
direction to senior project
management on scope, schedule,
budget, and standards, and monitor
the status of the project. Over time,
this project oversight role has
changed because of the formation
of the Transportation Financing
Authority. In fact, based on a review
of the minutes of the meetings and
interviews with committee members,
a project management consultant
noted that the Project Management
Committee was not fulfilling its
mandated terms of reference. The
future of the committee was under
review at the time of our audit.
The Technical Review
Committee was established to
provide guidance on technical
matters, make recommendations to
the Chief Highway Engineer about
proposed variances from standards,
and facilitate communication
34
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
between the Vancouver Island
Highway Project management
team and the rest of the ministry.
Membership consists of
representatives of each of the
Highway Engineering disciplines
(including Bridge Engineering,
Highway Safety, Highway
Environment), the Regional Director
for Region 6, and the Vancouver
Island Highway Project Manager or
Design Manager.
In July 1995, the consultant
engaged to review the Vancouver
Island Highway Project’s project
management practices concluded
that the Technical Review
Committee was “effective in
providing the communications
between Professional Services and
the Vancouver Island Highway
Project, ensuring the involvement
of Professional Services in approval
of Design Criteria early in the
design process, and facilitating
Vancouver Island Highway Project
design quality assurance.” We
observed, however, that the
committee has recently been less
effective, perhaps partly because of
the differing perspectives of the
project team and the rest of the
ministry. At the time of our audit,
discussions were taking place to
address the committee’s problems.
Communication
within the Ministry
Communications within the
ministry need to be improved.
During our audit, we noted some
tension between different groups
involved in the project.
Each group tends to perceive
issues in terms of its own concerns,
priorities, and accountability, rather
than seeing the issue from a ministry
perspective. The priorities of the
Vancouver Island Highway Project
staff emphasize building to scope,
meeting the schedule, and
minimizing capital and lifecycle
costs, with emphasis on minimizing
capital costs. Professional Services
staff are concerned with the integrity
of ministry design standards.
Ministry regional staff are concerned
about how improvements and
additions to the highway system
will affect long term maintenance
and rehabilitation costs.
These tensions are particularly
noticeable in the area of the
application of design standards. In
their efforts to minimize construction
costs, the Vancouver Island Highway
Project team has proposed
alternatives to design standards
which it believes will meet functional
requirements at a lower cost.
Ministry Professional Services staff
are reluctant to approve variations
unless they are convinced the
alternatives have equal performance
characteristics in both the short and
long terms. Ministry regional staff
are concerned that variations may
have negative implications for
maintenance and rehabilitation
costs—implications that will not be
evident until after the project has
been turned over to them. These
concerns are exacerbated by the fact
that the ministry does not have an
established analytical framework
(one that includes risk analysis and
cost-benefit analysis) by which such
concerns can be resolved.
Design Consultants
Consultants registered with
the ministry are invited to submit
proposals for design assignments.
The objective of the registration
and rotation system is to ensure
35
Auditor General of British Columbia
that consulting work is reasonably
distributed throughout the
consulting community. The
consultants’ credentials are reviewed
before they are placed on the list of
registered consultants, and each
consulting firm is assessed to
determine the maximum size of
contract on which it can bid.
The relationship between the
Vancouver Island Highway Project
and consultants is clearly described
in the terms-of-reference portion of
design contracts (which set out the
responsibilities of the parties).
The primary responsibility of
the consultants is to meet all the
milestones and produce all the
deliverables as required in the
terms of reference.
The consultants are also
required to provide quality control
over the design process to ensure
that designs meet functional
requirements and ministry
standards. In the past, the ministry
performed the quality control
function, reviewing consultants’
work and being closely involved in
design development. However, in
the case of the Vancouver Island
Highway Project, the project team
has concentrated instead on a
quality management (or quality
assurance) role, ensuring that
consultants have quality control
procedures in place and working
properly. All consultants must
submit a quality control plan with
their proposals and they are
responsible for submitting the
quality control reports they have
identified in their plan. The Design
Coordinator for the sub-project
visits the consultant’s office and
monitors compliance with the
consultant’s quality control plan.
Quality Assurance of
Consultants’ Work
Design reviews play an
important role in providing quality
assurance. The reviews may be
formal or informal, and they may
involve internal peer review or
review by outside consultants. It
is standard practice for new
consultants to review the work of
their predecessors when they take
over a design project as it moves
from one level of detail to the next,
and for design teams within the
consulting firm and within the
ministry to critically review designs
as they progress.
Review of the deliverables by
Design Coordinators and other
members of the project team
provides an opportunity to ensure
that the consultants are conducting
appropriate analyses and reviewing
all relevant options (subject to scope
and budget constraints) in terms of
cost and other project objectives.
Design Coordinators may also ask
ministry Professional Services staff
to review designs at any stage,
particularly if there are special
concerns.
There are no specific penalties
for poor performance by consultants.
If a contract is not going well, the
Project Manager may ask for
different staff to be assigned to the
job by the consultant. In extreme
cases, the Project Manager can
terminate the contract with the
consulting firm. In most cases,
however, there is negotiation until
ministry staff are satisfied that the
design meets requirements.
At the end of each design
assignment, Design Coordinators
are required to make reports to the
consultant registration system
36
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
administrator about the performance
of the consultants. If there has been
poor performance by a consultant,
the Design Coordinator is expected
to make a negative report. This
could result in the firm being
removed from the list of qualified
consultants or having its assessed
capability downgraded. However,
at this time, evaluations of past
performance are not always
considered when selecting
consultants.
Post-construction
Evaluation of Designs
Post-construction evaluations
of designs are a useful quality
improvement tool if the performance
results of designs are fed back to
consultants and ministry staff.
Although post-construction
reviews are conducted on the
Vancouver Island Highway Project,
they are mainly to identify problems
related to construction. They do not
include any analysis of the cost-
effectiveness of the designs, although
it is understood that designs that
are difficult to construct generally
result in higher costs.
The Environment Management
section of the ministry does conduct
post-construction evaluations that
look at the functional effectiveness
and cost-effectiveness of
environmental protection and
mitigation work for the purpose
of improving future efforts.
As well, the ministry monitors
the performance of its facilities
on an ongoing basis and this
experience may be reflected in
standards, although there is no
37
Auditor General of British Columbia
Big Qualicum River Bridge (near Parksville)
Courtesy: Ministry of Transportation and Highways
formal process for this. For the
most part, the feedback loops are
not well developed and ministry
staff are not well informed about
the performance of designs.
Consultants also receive little
feedback from the ministry about
the performance of their designs.
Recommendation
We recommend that the
ministry formally monitor the
performance of the highway system
over time in order to identify and
replicate, where practical, design
features that provide the most cost-
effective solutions to identified
highway transportation needs.
38
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
In order to ensure a reasonable
degree of consistency in the
highway system throughout the
province, the ministry has, over the
years, developed a number of
standards that predetermine how
recurring planning, design, and
construction issues will be handled.
These standards are intended to
ensure the planning, design, and
construction of highways that are
safe and reliable. We think they
should also ensure the planning,
design, and construction of
highways that are cost-effective
capital investments.
Our audit reviewed the
application of the ministry’s
standards to the Vancouver Island
Highway Project to determine if
they are likely to produce cost-
effective designs that meet the
needs of the project. We expected to
find planning and design standards
that are adequately documented,
consistent with similar standards in
other provinces, and regularly
reviewed and updated to
incorporate policy changes and new
technology. We also expected that
value for money would be a factor
in the development and application
of standards.
Conclusion
The planning and design
standards currently being used by
the ministry are generally adequate
from a technical point of view.
However, historically, the ministry
has placed more emphasis on safety
and reliability in the development
and application of its standards
than on their cost-effectiveness.
Consequently, although the design
process provides opportunity to
develop cost-effective design
alternatives to ministry standards,
there has been insufficient use of
formal cost-benefit and risk analysis
techniques to evaluate alternatives.
Findings
Planning Standards
Planning standards—
specifically, the guidelines for
the determination of functional
classification, design speed, and
planned level of service within the
design life of a highway—are major
determinants of the cost of a new
or upgraded highway. Potentially
greater savings are available from
reviews of these standards than
from changes to design standards.
Since June 1992, a major
decision in the highway planning
and design process has been the
determination of the functional
classification for a highway project
that is to be built. This decision is
now fundamental in determining
how a particular highway will be
configured and what it will cost.
The Highway Functional
Classification Study, described as
a guideline for planning highway
system development, establishes a
functional classification matrix
which groups highways into classes
according to the character of the
service they are to provide—for
example freeway, expressway, or
arterial highway. The character of
service reflects the relative emphasis
given to mobility (ease of passage)
on one hand and access (opportunity
to enter or exit the highway) on the
other hand.
39
Auditor General of British Columbia
standards
Two of the critical elements in
the determination of the appropriate
functional classification for a
highway are the forecast traffic
volume for the design life of the
highway (usually 20 years into the
future) and the targeted minimum
level of service during that period.
Level of service describes the
smoothness of the flow of traffic on
a highway and is categorized from
levels A to F (A being free-flowing,
low-volume traffic and D, E, and F
ranging from occasional traffic
congestion to stop-and-go conditions
with frequent long delays). Level of
service goals drive the calculations
that lead to the determination of
appropriate functional classification,
based on expected future daily
traffic volumes.
The type of terrain that the
highway will traverse is another
factor. The ministry categorizes
terrain types as level, rolling, or
mountainous. The levels of forecast
traffic volume that justify a certain
type and configuration of highway
vary according to terrain. For
example, more than 7,000 daily units
of traffic on mountainous terrain
suggest the need for a four-lane
freeway, whereas more than 14,000
units are required on level terrain.
Functional classification, and
therefore capital costs, could be
reduced by accepting a lower level
of service. A lower level of service
would result in increased likelihood
of traffic congestion during more of
the day. The ministry may determine
that the social and economic impact
of such congestion balance (or
outweigh) reduced capital costs.
However, the importance and value
of free-flowing traffic may be less,
in light of the current need for fiscal
restraint, than it was in the past. We
believe the ministry should
consider the impact that providing
a lower level of service would have
on the costs and benefits related to
highway construction.
Recommendation
The ministry should review
the planning guidelines contained
in the Highway Functional
Classification Study. In particular,
it should confirm that functional
requirements associated with the
current level of service goals—and
the costs associated with meeting
those requirements—are consistent
with government fiscal policies.
Design Standards
Once the functional
classification of a highway is
established, the highway’s physical
characteristics are determined by
application of the ministry design
standards. These standards are
contained in the Highway
Engineering Design Manual,
published by the Engineering
Branch.
The design manual is based on
design policies of the
Transportation Association of
Canada (TAC) and the American
Association of State Highway and
Transportation Officials (AASHTO).
The general purpose of TAC and
AASHTO policies and standards is
to promote uniformity of design
features, in the interests of
maintaining the overall well-being
of the travelling public through the
provision of safe roads. The
ministry manual represents the
ministry’s interpretation of, and
instructions on how to apply, these
policies to British Columbia
highway projects. Similar design
manuals exist in other Canadian
provinces and the United States, as
well as in other countries.
40
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
We found the documentation
of the standards to be adequate.
However, we also found that the
rationale underlying the standards
is not always clearly described in
the highway design manual. The
addition of more commentary
explaining the highway design
standards would be of assistance
to consultants when they are
contemplating a design variance.
The bridge design manual, on the
other hand, offers better commentary
and rationale for many bridge
design elements.
Reviews of Design Standards
Independent Review
In November 1994, the ministry
initiated a review of the ministry’s
highway design standards. A
consultant was hired to determine
if the standards could be changed
in order to reduce costs while
maintaining an acceptable level
of safety.
At the end of the review, in
March 1995, the consultant
concluded that “British Columbia
highway design standards are
adequate based on the comparison
to the standards of other
jurisdictions and the literature
reviewed” and that “current
Ministry of Transportation and
Highways geometric standards are
considered to be minimum
standards and reductions are
unwarranted.” The suggestion was
made that a way to reduce the
capital cost of highway construction
would be by staging construction to
match capacity to demand.
The report also concluded that
risk had not been systematically
addressed in all design standards,
and that assessment of risk was
important in the application of
design standards.
41
Auditor General of British Columbia
Overpass on Inland Island Highway
Courtesy: Ministry of Transportation and Highways
The report identified four areas
for further review: road grades, lane
width, clear zones alongside roads,
and shoulder and median widths.
Internal Review of Standards
After receiving the consultant’s
report, the ministry began a further
internal review of its standards. The
project team made a number of
recommendations related both to
the standards themselves and the
process for developing, reviewing,
and maintaining them. In particular,
it was suggested that the ministry
“create standards that are flexible
and permit deviation under certain
conditions.”
In January 1996, in response to
budget pressures, the review of the
ministry’s road design standards
was assigned a higher priority. The
terms of reference drafted for the
review called for the implementation
of all cost savings measures that
could be identified, and the
inclusion of both lifecycle and
initial capital costs in economic
analysis. Improved cost-effectiveness
in the application of standards was
also sought, including deviating
from standards if doing so would
result in a better design at equal or
less cost.
The review committee
produced a draft final report in
June 1996, in which it identified a
number of areas in which savings
could be realized by adopting
different standards. The committee
also identified additional standards
for review, including: instituting
narrower lane and shoulder widths;
reducing design speed in urban
areas and in rural areas with
extreme topographical constraints;
and basing clear zone requirements
on design speed and traffic volume
rather than highway classification.
We believe that the
ministry should continue to
review its technical standards with
a view to identifying further
opportunities to achieve greater
cost-effectiveness without unduly
compromising safety.
Ongoing Review of Standards
The process for reviewing
and updating standards is, itself,
presently being reviewed as a result
of the ministry downsizing that
was taking place at the time of
our audit. As part of a ministry
restructuring, the Standards Section
of the Highway Engineering
Branch was reduced from seven
staff to two.
During recent years, technical
standards have been reviewed
annually, with suggestions for
changes being submitted to the
Standards Section. The process has
been reactive, and driven mainly
by technical, rather than economic,
considerations. Cost-effectiveness
has not, over the years, been
systematically taken into
consideration in the development
or review of standards. This has
been changing, however, and cost-
effectiveness of design standards
has been considered in some cases.
For example, cost-effectiveness was
considered in the initial decision to
adopt current standards for clear
zones alongside highways. Lifecycle
cost considerations have also been
considered in some of the ministry’s
design standards. For example,
weathering steel is now being used
in bridge construction to avoid the
requirement for periodic repainting.
However, these standards were
developed based on the experience
and expertise of ministry staff,
rather than as the result of any
specific lifecycle cost analyses.
42
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Opportunity for Innovation
within Standards
As noted earlier in this report,
the establishment of the functional
classification of a highway, based on
forecast traffic volume, determines
much of the design characteristics of
the highway. During the preliminary
design process, design criteria are
established on the basis of the
functional classification of the
highway. Once the design criteria
are established, the designer has
only limited opportunity to produce
innovative designs; the ultimate
design solution involves meeting
the design criteria and design
standards.
Designers do not usually
attempt to produce innovative
designs that incorporate variances
to design standards. Using the
design standards, the designer
attempts to optimize the plan and
profile for the roadway (or roadways,
in the case of a divided highway or
interchange configuration) so that,
for example, minimum quantities of
fill need to be acquired, moved, or
removed from the project site. The
designer’s goal is to produce an
optimal design based on the design
criteria established for the project.
Currently it is the Technical
Review Committee that reviews
requests for variance from design
standards. Any variance must then
be approved by the Chief Highway
Engineer. This process is intended
to ensure that standards are applied
—and variances approved—in a
consistent manner.
The ministry’s Professional
Services staff state that they neither
expect nor desire rigid adherence to
standards, but rather want to ensure
that any deviation from standard is
appropriate and approved.
Conversely, Project Managers on
the Vancouver Island Highway
Project believe that the rest of the
ministry regards standards as being
prescriptive. The Project Managers
also believe that many of the
standards require practices that are
not cost-effective.
The approach of design
consultants is to be conservative in
developing designs because there is
little incentive to invest the time,
effort, and expense in developing
and justifying innovative approaches
to design.
We believe the ministry should
encourage designers to develop site-
specific design alternatives, including
variations to design standards,
where a more cost-effective design
can be achieved within the
appropriate performance and
safety requirements. Pavement
design, for example, is not tailored
to traffic and geotechnical conditions;
rather, the ministry’s “typical”
design is applied universally
regardless of conditions because
there is no incentive for designers
to perform the risk and cost-benefit
analyses required to support a
variance proposal.
Recommendation
The ministry should encourage
designers to consider cost-effective
alternatives that include variances
from ministry design standards.
Requests for variance from ministry
standards should be supported
by detailed risk and cost-benefit
analyses.
43
Auditor General of British Columbia
44
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1988
In 1988, Cabinet approved the Vancouver Island Highway Project in principle based on a general “order
of magnitude” estimate of cost.
1989
In January 1989, the ministry requested Treasury Board approval to proceed with a program of major
highway system improvements for Vancouver Island. Scope of the project was described as:
staged upgrading of the Pat Bay Highway, between the Swartz Bay ferry terminal and McKenzie Avenue,
to freeway status;
staged upgrading of the Trans Canada Highway, between Tillicum Road and Goldstream Park, to
freeway status;
completion of the Trans Canada Highway, between Goldstream Park and Nanaimo, to a multi-lane
arterial highway standard; and
construction of a new freeway-standard Inland Island Highway around the urban area of Nanaimo and
between Parksville and Campbell River.
The cost of the project, based on very preliminary engineering, was estimated to be something in excess
of $600 million (1988 dollars). It was proposed that work be completed by 1996.
In February 1989, Treasury Board advised the ministry that the request had been deferred pending more
detailed plans and cash flow projections.
1990
In January 1990, the ministry presented a package of alternatives for upgrading different sections of the
Vancouver Island Highway to Cabinet. This presentation was based on a submission to Treasury Board
that had been made in October 1989. The recommended scope for the project was:
upgrading Pat Bay Highway, from Swartz Bay to Saanich Municipal Hall, to four-lane freeway;
upgrading the Trans Canada Highway to Goldstream Park to four-lane freeway;
upgrading the Trans Canada Highway from Goldstream Park to Nanaimo to four-lane expressway;
building a new four-lane expressway through Nanaimo, plus the designing and acquiring right-of-way
for a freeway bypass; and
building a new four-lane freeway from Parksville to Menzies Bay.
The budget estimate for the recommended scope was $1,425 million (1989 dollars). The ministry
cautioned that the estimate was actually within a range of $1,150 million to $1,500 million. The work
was to be completed by 1996.
At the time of the presentation to Cabinet, Treasury Board had instructed the ministry to identify
significant reductions in program cost. Treasury Board set target levels of $1,100 million, $900 million,
and $700 million for the development of alternative project scope packages.
In May 1990, Cabinet approved a project scope that included: an expressway on the Pat Bay Highway,
freeway status on the Trans Canada Highway from Tillicum Road to Millstream Road, an expressway
from Millstream to Goldstream Park, an expressway from Goldstream Park to Nanaimo, an Inner Route
expressway through Nanaimo instead of the Nanaimo Bypass freeway, and an expressway from Parksville
to Menzies Bay north of Campbell River. Estimated cost of the project was $1,100 million (1989 dollars).
Exhibit 5
Scope, Schedule, and Budget for the Vancouver Island Highway Project
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
45
Auditor General of British Columbia
In May 1990, Treasury Board approved the project scope but requested further submissions concerning
total project budget, annual cash flow, and project completion date before final approval would be
given. Within the approved scope:
The Pat Bay Highway was to be upgraded to four-lane expressway standard, with interchanges at
McKenzie Avenue, Beacon Avenue, Island View Road, and Land’s End Road. The ability to expand the
highway south of Island View Road to six-lane freeway was to be protected.
The Trans Canada Highway was to be upgraded to four-lane freeway from Victoria to Millstream
Avenue, and four-lane expressway from Millstream Road to Goldstream Park, with interchanges at
McKenzie Avenue, Helmcken Road, and Highway 1A. There were to be intersections with signals at
Millstream Road and Amy Road. The ability to expand the highway east of Millstream Road to six lane
freeway and place an interchange at Millstream Road was to be protected.
Goldstream to Nanaimo was to be upgraded to four-lane expressway standard except between the
Shawnigan Lake Road and Bamberton, with frontage roads placed alongside existing four-lane sections
and median barriers to be installed on existing four-lane sections.
Highway 19 through Nanaimo and between Nanaimo and Parksville was to be maintained at its
current standard. A second route through Nanaimo was to be constructed to four-lane expressway
standard, with access limited to major intersections with signals. Necessary steps to protect a corridor
for a freeway bypass of Nanaimo were to be taken.
The inland route from Parksville to Menzies Bay was to be built to four-lane expressway standard from
Parksville to Courtenay, and to two-lane expressway standard from Courtenay to Menzies Bay. The
ability to expand the latter section to four lane expressway was to be protected.
1990–1993
As already stated, in May 1990 the budget was estimated to be $1,100 million (1989 dollars), based on
planning level information. The ministry expected that by September of that year it would be able to
upgrade the budget estimate for the project to a preliminary design estimate level. From May 1990 to
May 1993, the ministry continued to refine the scope, schedule, and budget for the project. During this
time, the ministry made several major scope revisions including:
deleting the Beacon Avenue interchange at the request of the Town of Sidney;
adding four-laning from the Malahat Summit to Bamberton;
downgrading the standards from Goldstream to Nanaimo to arterial standard;
extending the Nanaimo parkway northward from Mary Ellen Road to Superior Road;
connecting the parkway at Northfield Road rather than East Wellington Road at the request of the City
of Nanaimo; and
revising the connection at the north end of the Inland Island Highway.
The net effect of these scope changes was a reduction of $27 million. The ministry also recommended
the following additional scope changes:
adding an interchange at Millstream and the Trans Canada Highway;
upgrading Millstream Road to four lanes between the Trans Canada Highway and Goldstream Avenue;
extending Millstream Road south to Highway 14; and
simplifying the interchange at Thetis Lake overpass.
In May 1991, planning for the Victoria portion of the Trans Canada Highway and the Pat Bay Highway
ceased, pending the outcome of a Capital Regional District planning study. The results of the study were
presented in May 1994.
46
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
1993
In May 1993, the ministry estimated the budget for the project to be $1,226.4 million (1993 dollars).
In August 1993, Treasury Board approved a scope, schedule, and budget for the Vancouver Island
Highway Project. The approved scope was based on earlier submissions but included a number of scope
changes:
The Beacon Avenue interchange at Sidney was deleted, and the existing intersection was to be
improved.
The intersection of Millstream Road and the Trans Canada Highway was upgraded to an interchange.
The Millstream Connector, a four-lane arterial road from the Millstream Interchange to Highway 14,
was added to the project.
A new connector road was to be built north of the Victoria General Hospital.
The section of the Trans Canada Highway from Goldstream Park to Nanaimo was downgraded from an
expressway to a four-lane divided arterial highway.
The approved budget was $1,227 million (1993 dollars). The schedule called for completion of the
project in 1999.
1994
In November 1994, facing a budget overrun of $180 million (attributed to scope changes proposed by
the ministry and land acquisition costs, and annual spending limits imposed on the project) the
Transportation Financing Authority asked the ministry to identify opportunities to reduce the scope of
the project and the annual expenditures for the project. The ministry responded with alternatives that
delayed project completion or reduced the scope of the project, thereby reducing annual expenditure in
future years. Proposed scope changes included:
eliminating of any further work on the Pat Bay Highway, including the interchange planned for Island
View Road and improvements to the highway between Quadra Street and Martindale Road;
deferring the widening, lane separation, and reduction of the number of access points for the Trans
Canada Highway on either side of Goldstream Park; and
deferring some work on the northern portion of the Inland Island Highway, reducing some planned
four-lane sections to two lanes, and deleting some logging road grade separations.
1995
In January 1995, Treasury Board approved the Transportation Financing Authority’s recommended
reduction in scope and extended the completion date for the project to the year 2000.
In October 1995, the Transportation Financing Authority approved another scope reduction to keep the
project within the budget of $1,263.6 million (1995 dollars). The scope reduction substituted a
signalized intersection and flyover ramp from the Trans Canada Highway to McKenzie Avenue for the
planned full diamond interchange. This change will save $16 million.
1996
In 1996, the Transportation Financing Authority approved an addition of $12.3 million to the project for
the Duke Point Interchange—required to accommodate traffic that will be generated by the new ferry
terminal. With adjustments of $20.4 million to reflect inflation, the budget for the project is currently
$1,296.3 million (1996 dollars).
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
47
Auditor General of British Columbia
The Ministry is pleased to receive
the critique of the Auditor General
related to planning and design for the
Vancouver Island Highway Project. In
general, we agree with the “Overall
Conclusions” and concur with the “Key
Findings.” The Ministry is continually
looking to improve the way it conducts
its business and considers comments
from outside the Ministry as extremely
helpful as they provide a fresh
perspective.
Ministry Response to “Overall
Conclusions”:
The Ministry is pleased with
the conclusions that the Vancouver
Island Highway Project will provide
good value for money and that the
Ministry’s planning and design
standards are generally adequate.
It is also of value to receive your
opinion that the project team has
developed appropriate design
management processes, including
an adequate Quality Management
program.
We share the conclusion that
there was insufficient planning during
early phases of the project and that
subsequent work phases have
addressed most of these deficiencies.
Your conclusion that the
Ministry would benefit from a review
of standards and their application to
ensure cost-effectiveness is supported
and actions are underway to respond
to this finding.
Ministry actions to address
comments and recommendations from the
audit report:
The Ministry recognizes that there
was insufficient planning and
documentation of planning during the
early stages of the Vancouver Island
Highway Project, though most of the
deficiencies were addressed during the
subsequent planning and design
phases. In future, it is the firm
requirement of both the Ministry and
of the BC Transportation Financing
Authority that all potential projects
will have adequate early planning in
the form of system and corridor
planning, project needs identification,
analysis of alternative improvement
options and project scope/cost estimate
development. The Ministry is
currently developing policy and
procedure documents to facilitate
consistent planning practices.
Deliverables will be refinement of the
Provincial Highway Plan, regional
systems plans and highway corridor
plans and strategies to provide a
comprehensive context for project
justification and definition.
The Ministry agrees that the more
attention to estimating lifecycle cost is
appropriate for planning, design, and
standards development and review.
Lifecycle costing, and other formal
economic review techniques, are now
included in the Ministry’s planning
processes. In future, the Ministry
intends to incorporate into its design
processes, in addition to estimated
capital cost, the estimated lifecycle cost
of each alternative being evaluated.
ministry response
48
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
The Ministry agrees that formal risk
and cost-benefit analyses should be
developed for requests for variance
from standards by the project: to
document such requests, to improve
communication within the Ministry,
and to facilitate development of cost-
effective alternatives by designers that
include variances from design
standards.
The Ministry agrees that guidelines for
determining functional classification of
highways require ongoing review to
ensure cost-effectiveness and consistency
with government policies. The
Ministry recognizes that, historically,
it has placed emphasis on safety and
reliability in the development of its
design standards, and that there has
been insufficient use of formal cost-
benefit and risk analysis techniques in
standards development and review. As
noted in the report, the Ministry has
recently concluded external and
internal reviews of its design standards,
including consideration of both
lifecycle and capital costs to improve
the cost-effectiveness of standards. In
future, the Ministry intends to take a
more systematic and proactive
approach to standards reviews.
The Ministry agrees that the different
Ministry groups involved in the project
should view issues from an overall
Ministry perspective rather than
seeing them in terms of their own
concerns, priorities and accountability.
The groups within the Ministry are
working together to modify their
approach to the project, beginning with
understanding and considering issues
from each others’point of view.
The Ministry agrees that a formal
program to assess the functional and
cost-effectiveness of “as constructed”
designs and capture this experience
in its corporate memory would be
beneficial. The project is currently
developing processes for project close
out, including providing feedback to
the Ministry and consultants on
project management and technical
lessons learned. In future, the
Ministry intends to investigate
means to measure effectiveness of
“as constructed” designs from a
longer term perspective so that the
experiences may be communicated
throughout the Ministry.
It is apparent that the audit team
gained a solid understanding of the
planning and design processes as applied
to the Vancouver Island Highway Project
both in the late 1980’s as well as current
practice. This substantial appreciation of
the progressive enhancement of planning
and design processes has contributed in a
very tangible manner to the value of the
audit findings. We sincerely wish to
thank you and your staff for the
professional approach undertaken
throughout the audit.
appendices
49
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
51
Auditor General of British Columbia
1996/97 Audit Reports
Issued to Date
Report 1
Performance Audit
Management of
Child Care Grants
Report 2
Crown Corporation
Governance Study
Report 3
Performance Audit
Vancouver Island
Highway Project:
Planning and Design
appendix a
Office of the
Auditor General:
Audit Objectives
and Methodology
Audit work performed by the
Office of the Auditor General falls
into three broad categories:
Financial auditing;
Performance auditing; and
Compliance auditing.
Each of these categories has
certain objectives that are expected
to be achieved, and each employs
a particular methodology to reach
those objectives. The following is a
brief outline of the objectives and
methodology applied by the Office
for performance auditing.
Performance Auditing
Purpose of Performance Audits
Performance audits look at
how organizations have given
attention to economy, efficiency
and effectiveness.
The concept of performance
auditing, also known as value-for-
money auditing, is based on two
principles. The first is that public
business should be conducted in a
way that makes the best possible
use of public funds. The second is
that people who conduct public
business should be held accountable
for the prudent and effective
management of the resources
entrusted to them.
The Nature of Performance Audits
An audit has been defined as:
. . . the independent, objective
assessment of the fairness of
management’s representations on
performance, or the assessment of
management systems and practices,
against criteria, reported to a
governing body or others with
similar responsibilities.
This definition recognizes that
there are two primary forms of
reporting used in performance
auditing. The firstreferred to
as attestation reportingis the
provision of audit opinions on
reports that contain representations
by management on matters
of economy, efficiency and
effectiveness.
The secondreferred to as
direct reportingis the provision
of more than just auditor’s opinions.
In the absence of representations
by management on matters
of economy, efficiency and
effectiveness, auditors, to fulfill
their mandates, gather essential
information with respect to
management’s regard for value for
money and include it in their own
reports along with their opinions. In
effect, the audit report becomes a
partial substitute for information
that might otherwise be provided
by management on how they have
discharged their essential value-for-
money responsibilities.
The attestation reporting
approach to performance auditing
has not been used yet in British
Columbia because the organizations
we audit have not been providing
comprehensive management
representations on their
performance. Indeed, until recently,
the management representations
approach to value for money
was not practicable. The need to
52
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
appendix b
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
account for the prudent use of
taxpayers’ money had not been
recognized as a significant issue
and, consequently, there was
neither legislation nor established
tradition that required public
sector managers to report on a
systematic basis as to whether
they had spent taxpayers’ money
wisely. In addition, there was no
generally accepted way of reporting
on the value-for-money aspects of
performance.
Recently, however, considerable
effort has been devoted to
developing acceptable frameworks
to underlie management reports on
value-for- money performance,
and public sector organizations
have begun to explore ways of
reporting on value-for-money
performance through management
representations. We believe that
management representations and
attestation reporting are the
preferred way of meeting
accountability responsibilities and
are actively encouraging the use of
this model in the British Columbia
public sector.
Presently, though, all of our
performance audits are conducted
using the direct reporting model,
therefore, the description that
follows explains that model.
Our performance audits
are not designed to question
government policies. Nor do they
assess program effectiveness.
The Auditor General Act directs the
Auditor General to assess whether
the programs implemented to
achieve government policies are
being administered economically
and efficiently. Our performance
audits also evaluate whether
members of the Legislative
Assembly and the public are
provided with appropriate
accountability information about
government programs.
When undertaking performance
audits, auditors can look either at
results, to determine whether value
for money is actually achieved, or
at managements’ processes, to
determine whether those processes
should ensure that value is received
for money spent.
Neither approach alone can
answer all the legitimate questions
of legislators and the public,
particularly if problems are found
during the audit. If the auditor
assesses results and finds value for
money has not been achieved, the
natural questions are “Why did
this happen?” and “How can we
prevent it from happening in
future?” These are questions that
can only be answered by looking at
the process. On the other hand, if
the auditor looks at the process and
finds weaknesses, the question that
arises is “Do these weaknesses
result in less than best value being
achieved?” This can only be
answered by looking at results.
We try, therefore, to combine
both approaches wherever we can.
However, as acceptable results
information and criteria are often
not available, our performance
audit work frequently concentrates
on managements’ processes for
achieving value for money.
We seek to provide fair,
independent assessments of
the quality of government
administration. We conduct our
audits in a way that enables us to
provide positive assessments where
they are warranted. Where we
cannot provide such assessments,
we report the reasons for our
reservations. Throughout out
audits, we look for opportunities
53
Auditor General of British Columbia
to improve government
administration.
Audit Selection
We select for audit either
programs or functions administered
by a specific ministry or public
body, or cross-government
programs or functions that apply
to many government entities. There
are a large number of such programs
and functions throughout
government. We examine the larger
and more significant ones on a
cyclical basis.
We believe that performance
audits conducted using the direct
reporting approach should be
undertaken on a five- to six-year
cycle so that members of the
Legislative Assembly and the
public receive assessments of all
significant government operations
over a reasonable time period.
Because of limited resources, we
have not been able to achieve this
schedule.
Our Audit Process
We carry out these audits in
accordance with the value-for-
money auditing standards
established by the Canadian
Institute of Chartered Accountants.
One of these standards requires
that the “person or persons carrying
out the examination possess the
knowledge and competence
necessary to fulfill the requirements
of the particular audit.” In order to
meet this standard, we employ
professionals with training and
experience in a variety of fields.
These professionals are engaged
full-time in the conduct of
performance audits. In addition, we
often supplement the knowledge
and competence of our own staff by
engaging one or more consultants,
who have expertise in the subject of
that particular audit, to be part of
the audit team.
As performance audits, like
all audits, involve a comparison
of actual performance against a
standard of performance, the CICA
prescribes standards as to the
setting of appropriate performance
standards or audit criteria. In
establishing the criteria, we do not
demand theoretical perfection from
public sector managers. Rather, we
seek to reflect what we believe to be
the reasonable expectations of
legislators and the public. The
CICA standards also cover the
nature and extent of evidence that
should be obtained to support the
content of the auditor’s report, and,
as well, address the reporting of the
results of the audit.
54
Auditor General of British Columbia
1996/97 Report 3: Vancouver Island Highway Project: Planning and Design
Compiled and typeset by the Office of the Auditor General of British Columbia
and published by the Queen’s Printer for British Columbia
©
Victoria 1996